Building Blox: Week 9 – Roof, utilities started & Property Technology

What we did: First floor brickwork, Roof brickwork, Excavation started for utilities. It’s amazing how much the site has transformed over the past week. We’ve gone from a single-story building on Tuesday morning to a double story and part of a Read More …

Building Blox: Week 6 – Brickwork sees solid progress / The construction racket

What we did: Bricks delivery Beam and block floor installation Brickwork to ceiling Site management and Community service Whilst listening to the fantastic weekly property-technology podcast (warning: the theme-tune is weirdly catchy) I was reminded that… The industry is inefficient And Read More …

Building Blox: Week 4 – Bricks, blocks, beams and more bricks

What we did: Brickwork up to ground level Block and beam delivery Brick selection This week was another reminder that despite having a main contractor who on paper is responsible for conducting all the works… …in reality I have to take Read More …