Building Blox: Week 9 – Roof, utilities started & Property Technology

What we did: First floor brickwork, Roof brickwork, Excavation started for utilities. It’s amazing how much the site has transformed over the past week. We’ve gone from a single-story building on Tuesday morning to a double story and part of a Read More …

Building Blox: Week 2 – The big concrete foundation pour

What we did: Excavations (part 2), Installed steel and Claymaster, Site prep for pour, Concrete pour.
A huge, exciting week as we stepped into a new chapter with the concrete pour. Read More …

Building Blox: Week 1 – Site set up, demolition and start of excavations

What we did: Finalise contracts, Fence off site and set up facilities, Health and safety checks/notifications/signage, Demolition of existing garages, Site scrape, Surveyor’s setting out, Excavations (part 1).
What felt like a lot longer than a week saw some pretty solid progress! Read More …